摘要:三峡主体工程的混凝土总量达2800万m3,其中大坝混凝土约2000万m3。大坝混凝土施工是三峡工程能否按照总进度的要求达到计划目标的关键。根据总进度安排,其年最高浇筑量要达到500万m3,月最高要达到40万m3,日最高应达到万m3以上。经过对施工手段的多方案比较分析,在充分论证的基础上,决定选用以塔式皮带机连续输送浇筑为主,辅以大型门塔机和缆机的综合施工方案。在仓面工艺设计中,采用了平浇法和台阶法,同时,改革传统工艺,提出并运用塔(顶)带机新工艺。 关键词:混凝土;快速施工;方案及工艺;三峡工程 Abstract: The main body of the Three Gorges project concrete total of 28,000,000 m3, one of the concrete dam of about 20,000,000 m3. Concrete construction is the Three Gorges Dam project can progress in accordance with the requirements of the overall plan to achieve the key objectives. According to the progress of the total, in its capacity to achieve the highest placement 5,000,000 m3, to achieve the highest on 400,000 m3, and Japan should meet the highest for more than 20,000 m3. After the construction of more than a means of a comparative analysis of the program, with full proof on the basis of the decision to choose transmission tower belt machine pouring in a row, supplemented by a large gate tower and cable machine comprehensive construction plan. On deck in the design process using a water-level law and law at the same time, the reform of traditional crafts, and made use of towers (top) with the new machine technology. Key words: concrete; rapid construction; programs and technology; the Three Gorges Project