刚好我也在做毕业设计 把我的给你用吧! Traditional Construction ProceduresAs mentioned before, construction under the traditional construction procedure is performed by contractors. While they would like to satisfy the owner and the building designers, contractors have the main objective of making a profit. Hence, their initial task is to prepare a bid price based on an accurate estimate of construction costs. This requires development of a concept for performance of the work and a construction time schedule. After a contract has been awarded, contractors must furnish and pay for all materials, equipment, power, labor, and supervision required for construction. The owner compensates the contractors for construction costs and general contractor assumes overall responsibility for construction of a building. The contractor engages subcontractors who take responsibility for the work of the various trades required for construction. For example, a plumbing contractor installs the plumbing, an electrical contractor installs the electrical system, and an elevator contractor installs elevators. Their contracts are with the general contractor, and they are paid by the general , in addition to a general contractor, the owner contracts separately with specialty contractors, such as electrical and mechanical contractors, who perform a substantial amount of the work require for a building. Such contractors are called prime contractors. Their work is scheduled and coordinated by the general contractor, but they are paid directly by the also, the owner may use the design-build method and award a contract to an organization for both the design and construction of a building. Such organizations are called design-build contractors. One variation of this type of contract is employed by developers of groups of one-family homes or low-rise apartment buildings. The homebuilder designs and constructs the dwellings, but the design is substantially completed before owners purchase the of the construction procedure often is difficult. Consequently, some owners seek assistance from an expert, called a professional construction manager, with extensive construction experience, who receives a fee. The construction manager negotiates with general contractors and helps select one to construct the building. Managers usually also supervise selection of subcontractors. During construction, they help control costs, expedite equipment and material deliveries, and keep the work on schedule. In some cases, instead, the owner may prefer o engage a construction program manager, to assist in administrating both design and contractors employ labor that may or may not be unionized. Unionized craftspeople are members of unions that are organized by construction trades, such as carpenter, plumber, and electrician unions, Union members will perform only the work assigned to their construction, all work should be inspected. For this purpose, the owner, often through the architect and consultants, engages inspectors. The field inspectors may be placed under the control of an owner’s representative, who may be titled clerk of the works, architect’s superintendent, engineer’s superintendent, or resident engineer. The inspectors have the responsibility of ensuring that construction meets the requirements of the contract documents and is performed under safe conditions. Such inspections may be made at frequent addition, inspections also are made by representatives of one or more governmental agencies. They have the responsibility of ensuring that construction meets legal requirements and have little or no concern with detailed conformance with the contract documents. Such legal inspections are made periodically or at the end of certain stages of construction. One agency that will make frequent inspections is the local or state building department, whichever has jurisdiction. The purpose of these inspections is to ensure conformance with the local or state building is a description of the basic traditional construction procedure for a multistory the award of a construction contract to a general contractor, the owner may ask the contractor to start a portion of the work before signing of the contract by giving the contractor a letter of intent or after signing of the contract by issuing a written notice to proceed. The contractor then obtains construction permits, as required, form governmental agencies, such as the local building, water, sewer, and highway general contractor plans and schedules construction operations in detail and mobilizes equipment and personnel for the project. Subcontractors are notified of the contract award and issued letters of intent or awarded subcontracts, then are given, at appropriate times, notices to construction starts, the general contractor orders a survey to be made of adjacent structures and terrain, both for the record and to become knowledgeable of local conditions. A survey is then made to lay out offices for the contractor are erected on or near the site. If desirable for safety reasons to protect passersby, the required to be removed from the site are demolished and the debris is carted , the site is prepared to receive the building. This work may involve grading the top surface to bring it to the proper elevations, excavating to required depths for basement and foundations, and shifting of utility piping. For deep excavations, earth sides are braced and the bottom is construction starts with the placement of foundations, on which the building rests. This is followed by the erection of load-bearing walls and structural framing. Depending on the height of the building, ladders, stairs, or elevators may be installed to enable construction personnel to travel from floor to floor eventually to the roof. Also, hoists may be installed to lift materials to upper levels. If needed, temporary flooring may be placed for use of the building rises, pipes, ducts, and electric conduit and wiring are installed. Then, permanent floors, exterior walls, and windows are constructed. At the appropriate time, permanent elevators are installed. If required, fireproofing is placed for steel framing. Next, fixed partitions are built and the roof and its covering are put is place,Finishing operations follow. There include installation of the following: ceilings; tile; wallboard; wall paneling; plumbing fixtures; heating furnaces; air-conditioning equipment; heating and cooling devices for rooms; escalators; floor coverings; window glass; movable partitions; doors; finishing hardware; electrical equipment and apparatus, including lighting fixtures, switches, transformers, and controls; and other items called for in the drawings and specifications. Field offices, fences, bridges, and other temporary construction must be removed from the site. Utilities, such as gas, electricity, and water, are hooked up to the building. The sit is landscaped and paved. Finally, the building interior is painted and owner’s representatives then give the building a final inspection. If they find that the structure conforms with the contract documents, the owner accepts the project and gives the general contractor final payment on issuance by the building department of a certificate of occupancy, which indicates that the completed building meets building-code requirements.传统的施工程序众所周知,在传统的施工程序中进行施工的承包商。尽管他们想满足业主和建筑设计师的要求,但是最终还是以赚取利润为主要目标的。因此,他们最初的任务是对编写投标价格的建筑成本进行准确的估计。这就需要进行前期调查的工作并且做出施工时间表。等合约批出后,施工方必须提供所有材料并支付其费用,设备,电力,劳动力。业主此时需要进行必要的监督。一个总承包商承担一个建筑整体的责任。从事分包的承建商则需承担建造工程所需的各个工作。例如,管道承包商安装水管,电业承办商安装电气系统,电梯则由电梯承包商安装。他们与总承包商签订合同,费用由总承包商支付。有时候,除了一个总承包商,还有各种专业承包商,如电气和机械承包商,执行工作时需要与业主签订合同。这种承包商被称为间接承包商。他们的工作,由总承包商协调,但它们都是由业主直接联系。还有些时候,业主可以使用设计建造方法同时兼有设计和建筑施工单位的职能。这些单位被称为设计建造承包商。这方面的一个类型的合同聘用的变化是由一户住宅或低层住宅建筑群的开发。在房屋建筑设计和建造的住房,但设计之前需要由购买房屋的业主完成。施工过程管理往往是困难的。因此,一些业主会去寻求专家的协助,这些专家被称为专业施工经理,他们具有丰富的施工经验。施工经理与总承包商进行谈判,并选择其中一个项目。施工经理通常还监督分包商。在施工期间,它们有助于控制成本,加快运送设备和材料,并保持工作的进度。在依法行政,协助设计和建设的情况下,业主可以选择从事建筑项目经理。建筑承包商雇用的劳动力,一般有大工和小工。大工再建筑工程中从事技术活,如木工,管道工,工会成员和电工工会,小工则执行了分配给他们的工作。在施工期间,一切工作都要验收。因此,业主通过建筑师和监理经常进行督查。可能是名为工程员,建筑师或驻地工程师。作为业主的代表实地视察。核查人员必须确保工程符合合同文件的要求,并在安全的条件下进行的责任。这种检查可作出重复。此外,验收还是需要一个或多个政府机构的代表。他们必须确保工程符合法律要求,并负责检查与合同文件是否一致。这种视察一般定期或在某些阶段施工结束以后进行。地方或国家建设部门具有管辖权。这些检查的目的是确保符合当地或国家的建筑规范。以下是传统多层建筑施工的基本程序。建造开始后合同授予开发商,业主可要求开发商开始施工之前签约给或之后签约发出书面通知的同时另一部分工作继续进行。紧接着施工方根据需要获取建筑许可证,例如当地的建设,供水,污水处理,政府机构和公路部门。总承包商的计划和进度详细施工作业以及动员项目设备和人员。分包商得到通知后,做出签订合同的意向或授予分包合同书,然后给出在适当的时候进行通知。在施工前启动,总承包商要进行的一项调查就是邻近结构和地形,这些都要记录在案,并要熟悉当地情况。这项调查结束以后,随即进行布局建设。承建商的现场办事处都建在施工现场或附近。为了安全起见,必须从脚手架上移除的东西,产生的碎片都要运走。下一步,该网架是为建设工程准备的。这项工作为地下室开挖和基础开挖的深度,以及公用事业管道转移找到正确的标高。深挖掘,土方支撑,底部排出。建筑开始于基础上,然后是承重墙和结构框架的施工。梯子,楼梯,或电梯的安装,可让施工人员往返于各个楼层。此外,可安装卷扬机来运送材料。由于建筑高度的上升,管道,电力管道和线路安装以及永久地板,外墙,窗户和构造的影响。在适当的时候,永久的电梯安装。再需要的情况下可以安装防火卷帘。其次,屋顶等地方也需要安装。精加工工序安装有包括以下内容:天花板,瓷砖,墙板,墙壁镶板,水管装置,加热炉,空气调节设备,加热和冷却室装置;自动扶梯;地板,窗户玻璃;活动板,门;电气设备和仪器,包括照明灯具,开关,变压器,控制器,遵照项目的图纸和规格。外地办事处,围栏,桥梁和其他临时建筑,公共设备,如天然气,电力管道,水管,都连接到建筑上。最后,是建筑物内部的打扫和清洗。业主的代表,会给建设工程作最后检查。如果他们满意并认为符合合同文件,那么业主接受该项目,并交给总承包商的一个占用证书,这表明,总承包商已完成建设,建设部门再根据建筑规范的要求发放最后付款。请采纳。
土木工程毕业论文参考文献
导语:随着科学技术的进步和工程实践的发展,土木工程这个学科也已发展成为内涵广泛、门类众多、结构复杂的综合体系。对我们的生活产生深远的影响。下面是我分享的土木工程毕业论文的参考文献,欢迎阅读!
土木工程毕业论文参考文献 篇1
1.《建筑结构制图标准》GB/T50105-2001
2.《建筑结构荷载规范》GB5009-2001(2006版)
3.《混凝土结构设计规范》GB50010-2002
4.《建筑地基基础设计规范》GB5007-2002
5.《砌体结构设计规范》GB5003-2001
6.《建筑抗震设计规范》GB5011-2001
7.《钢结构设计规范》GB50017-2003
8.《建筑结构构造资料》(合订本),中国建筑工业出版社,1998年。
9.《混凝土结构构造手册》,中国建筑工业出版社,2002年。
10.《地基基础设计手册》,上海科技出版社,1998年。
11.《混凝土结构设计手册》,中国建筑工业出版社,2002年。
12.《建筑结构静力计算手册》,中国建筑工业出版社,1999年
13.《建筑结构强制性国家标准》(简装本),中国建筑工业出版社,2001年9月
14. 任全宏、常建军.钢筋混凝土多层框架结构房屋结构设计中应注意的几个问题。陕西建筑2007,145(7).
15. 范俊梅. 钢筋混凝土多层框架结构设计问题分析. 科技资讯2008,3.
16. Basic Principles for Reinforced Concrete Structure Design
17.建筑、结构设计有关图集资料以及专业课程教材等。
土木工程毕业论文参考文献 篇2
[1] 齐骥, 徐波. 建筑工程管理学[M]. 陕西科学技术出版社.2003
[2] 刘正周. 管理激励. 上海财经大学出版社.1999 年 1 月
[3] 刘志远, 林云. 现代企业激励机制.上海人民出版社.1997 年,第 6 页
[4] 李旭伟. 总承包体制下项目质量管理研究[J]. 科技管理研究.2006(04)
[5] 侯光明. 管理激励与约束.北京理工大学出版社.1999 年,第 80 页
[6] 杨红军. 非正式制度与企业文化研究.吉林大学 2004 年硕士论文
[7] 姜敢闯. 现代企业激励问题研究.中南大学 2002 年硕士论文
[8] 张婷. 中西方管理特点比较分析. 山东大学 2009 年硕士论文
[9] 张曼玲. 企业内部会计控制研究.首都经济贸易大学 2004 年 3 月.
[10] 陈郁.所有权、控制权与激励. 上海三联书店、上海人民出版社.1998 年
[11] 齐骥, 徐波. 香港的建筑管理制度[J]. 建筑,2002(2):50-52.
[12] 戚安邦. 现代项目管理[M]. 北京:对外经济贸易大学出版社,2001 年.
[13] 王宗昌. 建筑工程质量控制实例[M]. 科学出版社.2004
[14] 王宗昌, 高振东. 建筑工程质量百问[M]. 北京:中国建筑工业出版社.1999
[5] 朱宏亮. 项目进度管理[M]. 北京:清华大学出版社,2002 年.
[16] 刘迎心, 李清立. 中国建筑工程质量现状剖析、国际借鉴、未来对策[M]. 中国建筑工业出版社.2007
土木工程毕业论文参考文献 篇3
[1] 张飞涟,周继祖.铁路建设项目后评价理论体系的研究[J].综合运输,2010(12) :25-28
[2] 黄 恺.积极开展商业房地产项目后评价[J].城市开发.2011(10): 76
[3] 汪红霞,商业地产项目引入后评价的探讨[J].重庆教育学院学报,(6):93-95
[4] 曲琳莉.正确进行商业房地产项目后评价研究[J].特区经济.2011(10), 299
[5] 曾珍香.可持续发展协调性分析[J].系统工程观论与文践,2011(3): 18-21
[6] 倪枫杰,黄金枝.工秤项目后评价研究综述[J].建筑技术开发,2009,31(11):103-106
[7] 许晓峰,肖 翔.建设项目后评价[M].中华工商联合出版社,2000
[8] 吕军印.浅谈环境经济评价的类别划分[J].中国环境保护.
[9] 张三力.项目后评价[M].清华大学出版社,2003
[10] 王 超.项目决策与管理[M].中国对外经济贸易出版社.2005
[11] 曹炳元.应用模糊数学与系统[M].中国:科学出版社,2005
[12] 戚成邦.项目评估学[M].大津:南开大学出版社.2006
[13] 徐 强.技术经济学原理与方法[M].北京:北京科学技术出版社.1993
土木工程毕业论文致谢
首先要向恩师表示衷心的感谢和深深的敬意。在两年半的研究生生活中,于老师无论是在学习上、工作上还是生活上都给了我极大的帮助,在为人处事上给予了我很大的启发。尤其是在本论文的创作过程中,从论文的选题、材料的`准备、开题、一直到论文撰写的整个过程,于老师都给予了我认真的检查和悉心的指导,于老师的这种严谨认真的治学态度,对我论文创作的整个过程都起到了巨大的推动作用。她严谨的治学精神、勤奋的工作态度和谦虚的处事风格无不时刻激励着我、启发着我,在今后的工作、生活和学习中我要更加勤奋努力、锐意进取。
其次,我要由衷的感谢许骏老师对我论文前期准备工作的指导以及在深入企业调研和实施过程中,我的校外导师及中国建筑工程第八工程局有限公司的领导和同事们给我的帮助以及给我提供的宝贵资料。同时,我还要感谢我的家人、朋友和同学们对我论文写作提供的支持和帮助。
最后,我要向在百忙之中抽出时间对本文进行评审和参加我答辩并提出宝贵意见的各位老师和专家表示衷心的感谢!
224 浏览 3 回答
143 浏览 3 回答
102 浏览 4 回答
146 浏览 3 回答
117 浏览 1 回答
176 浏览 3 回答
85 浏览 3 回答
217 浏览 3 回答
343 浏览 3 回答
253 浏览 4 回答
131 浏览 2 回答
358 浏览 3 回答
316 浏览 2 回答
107 浏览 3 回答
105 浏览 3 回答