(五)护壁泥浆的拌制1、护壁泥浆要用优质泥浆,保持桩孔不坍、不缩,尤其对较厚的填土及淤泥质土要采用优质泥浆。2、在钻进时,由于旋挖钻机为静态泥浆无循环钻进,且成孔速度快,护壁泥皮薄,据地质勘查资料知本场区存在较厚的软塑性粘土层和粉砂地层,易造成缩孔和塌孔的事故,因而钻进时对泥浆性能要求较高。为了满足施工要求,在制作泥浆时,应注意以下几点:(1)膨润土必须充分水化搅拌,保证浆体均匀一致。造浆后应静置24小时之后方可使用,保证膨润土的充分水化,泥浆各项指标符合要求。(2)泥浆絮凝或沉淀过多时,泥浆必须用空压机送风反复搅动,符合要求后才可送入孔内使用,否则势必会造成孔内沉渣过多或其它孔内事故。(3)为了保证安全连续正常施工确保成孔速度、成孔质量及灌注成桩质量,开孔前泥浆总量应达到设计方量的倍左右方可开钻,质检员、技术员要随时观察泥浆性能的变化,及时检测泥浆的性能,不符合设计要求的泥浆禁止送入孔内,钻进时及时足量补充孔内泥浆,防止孔内泥浆落差太大,即泥浆液面深度低于护筒进浆口30cm以下,而造成孔壁坍塌。尤其不允许浆面落到护筒底以下。在雨天施工时,应注意泥浆性能的变化,及时根据实际情况调整泥浆原料的配比。钻机因故停钻时(如机械故障、修理钻具等),要及时向孔内补充泥浆,保持泥浆高度,以保证孔内安全。二次清孔时沉淀池泥浆容量要大,保证清孔时孔内大量泥沙的有效沉淀,使二次清孔达到设计要求,禁止孔内泥浆低于护筒溢浆口。比重 粘度(S) 含砂量(%)~ 16~22 ≤4(4)施工中做好现场泥浆配置、排污、更换工作,设专人进行泥浆管理,保持泥浆比重在~之间。随时跟踪、检查循环池内泥浆比重、粘度,确保钻进需要。泥浆指标如表: (5)对于固相含量过高,比重、粘度超过规定值,不宜稀释处理的废浆应及时排运出场外处理。(6)当地下水位较高时,为保证钻孔过程不坍孔、缩孔,必须保证孔内水头,且要将泥浆比重调大。在钻进过程中,要及时补浆,确保钻进过程中的水头高度。(7)在泥浆池边设好防护安全栏。(8)为了保护环境,钻孔泥浆经沉淀处理合格后将钻渣运往指定地点。(六)钻孔1、准备好以上工作后,请监理工程师现场检查,钻机开始钻进施工。2、由施工经验丰富的同志担任机班长,负责成孔钻进设备的操作,并对机长进行钻进注意事项交底,强调机长对地质状况进行掌握,要求将地质剖面图和柱状图悬挂在操作室,掌握每根桩的地质情况,根据实测深度并对照地层埋深,判断钻进进度,在地层变化处附近,捞取钻渣样品与地质资料核实,以精确控制换层时的钻进参数,确保成孔质量。3、开钻时应慢速钻进,待导向部位或钻头全部进入地层后,方可加速钻进。但是对于加夹层(粉砂层)钻进时,需要调整泥浆比重到左右,并且采取慢速钻进的方法进行施工。4、旋挖机钻进过程中,钻杆要保持垂直状态,严格控制垂直度在规范允许范围之内。5、钻机钻进过程中应采用减压钻进,即钻机的主吊钩始终要承受的钻压不超过钻具重力之和(扣除浮力)的80%。6、要安排专人定时检查孔内泥浆水头高度,发现不足并及时足量补充。钻孔内泥浆水头高度应不低于护筒排浆孔下30cm,并高于地下水位2米。7、合理控制起钻和下钻时速度,避免激动压力和抽吸力对孔壁的影响。 8、在提钻头除土或因故停钻时,应保持孔内具有规定的水位和要求的泥浆相对密度和粘度。处理孔内事故因故停钻,必须将钻头提出孔外。对于地质状况发生大的变化,旋挖钻机不能钻进时,及时更换小钻头试钻,如果还是不能继续钻进,需要换旋转钻机或冲击钻时,立即派人24小时内调用钻机进场,确保孔壁不坍塌,或发生其他以外情况。9、做好钻孔施工记录,记录必须与实际工序同步,真实、齐全、整洁。孔深、钻速、换层特别是持力层应记录清楚。(七)成孔检测及清孔1、钻孔达到设计标高后,对孔深、孔径进行检查,符合规范要求后方可清孔,准备下钢筋笼。孔深采用测绳进行测量,测绳必须经常进行校正、修订,以保证测量准确。孔径采取下探孔器的方法进行检查,探孔器直径为钢筋笼直径+,探孔器的长度为设计直径的4~6倍。成孔深度和孔径不小于设计值,泥浆比重、含砂率及粘度由试验人员在现场进行测定,泥浆比重为~以内,含砂率小于4%,粘度为16~22s,以上均符合要求后,并经监理工程师验收合格后,才允许钻机移位,并准备清孔、下钢筋笼。2、清孔可采用抽浆方法,在清孔排渣时,必须保证孔内水头高度,防止塌孔。清孔后孔底沉渣厚度不大于100mm,合格后在孔底提出泥浆式样进行性能指标试验,试验结果必须符合相关技术标准要求。钻孔桩成桩检测标准序号 项 目 允 许 偏 差1 孔 径 不小于设计孔径2 孔 深 不小于设计孔深3 孔位中心偏差 不大于50mm4 倾 斜 度 不大于1%5 灌注混凝土前孔底沉渣厚度 不大于设计要求(八)钢筋笼制作、安装1、钢筋笼所用钢筋规格、材质及各项性能指标均应符合设计及规范要求,有出厂证明或检验报告单。原材料进场堆放在钢筋底部衬垫枕木上,确保钢筋堆放离地面高30cm,保证底部排水畅通。钢筋放置过程中,需采用彩条布遮盖防雨防尘。现场施焊的焊缝应按规范要求并抽检试验。 2、设专用胎架和施工平台,按照设计图纸将钢筋笼按要求分段制作,加强箍筋间距按≤2m设置。3、钢筋加工严格按照设计图纸和相关技术规范的要求执行,主筋在制作前必须整直,整直后钢筋弯曲度应不大于长度的1%,并不得有局部弯折。主筋一般应尽量用整根钢筋,分段后的钢筋笼主筋接头应互相错开,接头长度内,同一根钢筋不得有两个接头,配置在接头长度内的受力钢筋,其接头截面积占总截面积百分率小于50%(接头长度为35d)。4、成型钢筋笼吊放、运输、安装,应采取预防变形措施,不得产生运输变形。为防止钢筋笼在吊装、运输、安装过程中变形,对钢筋笼加强筋处进行交叉加固,加固方式采取在钢筋笼内加十字撑的方式,并焊接牢固,当钢筋笼安装就位后将其拆除。钢筋笼分节起吊连接时,采用25t或35t汽车吊机大小钩配合起吊,并将吊点处采用扁担加固并起吊,以防止钢筋笼变形。5、按顺序逐节垂直下放钢筋笼,上下节钢筋笼各主筋应对准校正,节段间在孔口采用帮条焊接方式对称施焊,焊接长度满足规范要求。下钢筋笼时间要尽量缩短,并每隔2米在同一截面上按90度对称安置4个钢筋保护筋。6、桩基检测声测管采用Ф51mm热轧无缝钢管,壁厚3mm。安装声测管钢筋笼的要求将声测管伸入桩底部并用薄钢板堵焊,每隔2m用5号铁丝将声测管绑扎在主筋上及在加强钢筋上焊钢筋环固定,将声测管分节焊接,焊缝牢固、饱满,确保声测管不漏水、不泌水。将声测管内灌满水后,将上部用薄钢板堵焊,以防止钻孔泥浆或混凝土砂浆进入声测管而影响桩基检测。声测管焊接时,必须采用小焊条,防止将声测管焊破漏水。7、钢筋笼起吊时,吊点应拴牢并布置合理,使笼子吊起后处于自然铅垂状态,并无明显变形,下吊钢筋笼骨架过程中,不要碰撞孔壁,要采取措施让其沿孔中心垂直插入。在钢筋笼外侧焊设计图纸上的定位钢筋,以保证保护层的厚度。吊放钢筋骨架入桩孔时,均匀下落,保证钢筋笼居中。钢筋笼下到标高后,要检查钢筋笼顶部的中心偏差,使之<5cm,待全部入孔经确认符合要求后,将钢筋笼进行固定,避免下沉和灌注混凝土时上浮。8、钢筋骨架制安精度要求见下表:钻孔桩钢筋骨架制作安装标准序号 项 目 允 许 偏 差1 钢筋骨架在承台内埋置长度 ±100mm2 钢筋骨架直径 ±20mm3 钢筋间距 ±(d为钢筋直径)4 加劲筋间距 ±20mm5 箍筋间距或螺距 ±20mm6 钢筋骨架垂直线 1%(九)下导管、二次清孔1、下导管混凝土灌注导管采用快速卡口垂直提升导管。导管使用前进行试拼、水密承压和接头抗拉试验、长度测量、标码等工作,进行水密试验的试压压力不应小于6kg/cm2。导管内壁应光滑平顺,连接紧直,使用一段时间后,应检查其水密性。导管下孔时,必须加密封圈并抹黄油,保证密封,孔内导管必须丈量准确,满足孔深要求,下端出口处应距孔底20-40cm。吊装时,导管位于井孔中央,避免挂碰钢筋笼,并在灌注前进行升降试验。坚持实行导管使用的检查鉴证制度。提升导管时要掌握每次的提升高度,保证埋入深度2~6m,以免混凝土“洗澡”。卸下的导管要及时冲刷干净,绝不允许在连接处和丝扣处有水泥砂浆残留,并按一定编号放置。2、二次清孔导管就位后,立即进行第二次清孔,清孔采取气举反循环进行清孔,清孔后沉渣必须小于100mm才允许灌注混凝土。清孔时要适当转动和升降导管,以利于孔底边部钻渣清出,并注意空压机的送气量,以满足清出沉渣的要求。取泥浆样测试合格,并经监理共同检测孔底沉渣达标后应立即灌注混凝土,若等待时间过厂则在灌注混凝土前重新测定孔底沉淤厚度。(十)混凝土水下灌注1、桩身混凝土采用商品混凝土、砼搅拌车直接送入仓的方法施工。采用导管法进行水下灌注。2、灌注混凝土前应将灌注机具如储料斗、溜槽、漏斗等准备好。3、水下混凝土灌注必须保证良好的和易性,坍落度18cm~20cm,混凝土到达现场后,现场试验室值班技术员在现在再做坍落度试验。4、采用罐车运输混凝土至现场,直接倒入导管内进行灌注,混凝土接近桩顶时,改用吊斗倾倒以提高漏斗高度。5、灌注时要求首批混凝土方量应能满足导管首次埋置深度≥1m和填充导管底部的需要,具体首批混凝土计算见下式:所需混凝土数量可参考公式: V≥ (H1+H2) + h1式中:V-首斗混凝土方量(m3); D-桩孔直径(m); H1-桩孔底至导管底端间距,一般为;H2-初次导管埋深m,取; d-导管内径m; H-灌注混凝土时孔深度m; h1-桩孔内混凝土达到埋置深度H2时导管内部混凝土柱平衡导管外;根据公式HWr1=h1r2计算,其中r1为泥浆的比重,取;r2为混凝土的比重,取,h1按最大孔深度H计算,即考虑最不利情况。 桩径最大孔深度H布置及V的计算序号 直径(m) 最大孔深的墩位 最大孔深(m) h1(m) 导管直径(m) 首斗砼方量V(m3)1 Z154 Z171 Z140 、混凝土通过砼搅拌车运送到作业地点后,用汽车起重机配合灌注。为了保证混凝土灌注顺利进行,施工中作好下列工作:(1)灌注水下混凝土前,探测孔底沉淀物厚度,如不能满足要求,则要利用导管按反循环法进行再次清孔。(2)砍球前准备足够的混凝土储备量,保证砍球后导管的埋置深度大于1m以上。(3)砍球前,导管距孔底的高度适当,一般取20~40cm。(4)灌注过程中,注意观察导管内混凝土面下降和孔内水位升降情况,及时测量孔内混凝土面高度。(5)导管埋置深度适当,保证埋置深度不大于6m ,且不小于2m。导管提升缓慢,不挂钢筋笼。(6)混凝土灌注到达钢筋笼底部以下约1m时,适当放慢灌注速度,减小混凝土的冲击力,防止钢筋笼上浮。当混凝土上升到钢筋笼底部以上4m左右时,提升导管,使其底口高于钢筋笼底部2m以上,可恢复正常灌注速度。(7)灌注作业连续进行,不得中途停顿,保证整桩在混凝土初凝期内灌注完成。(8)发现问题,及时分析原因,果断采取措施,避免发生断桩事故。(9)混凝土灌注至桩顶以后,超出设计桩顶30~50cm,然后及时将已离析的混合物及水泥浆等清除干净。(10)每桩按照规范要求取试件2~4组,当桩身混凝土达到其设计强度的70%后,检测桩身混凝土的质量。(11)钻孔桩质量控制标准见下表:钻孔灌注桩实测项目项 次 检 查 项 目 规定值或允许偏差值1 混凝土强度(Mpa) 在合格标准内2 桩 位(mm) 群 桩 100 排 架 桩 503 倾 斜 度 1%4 沉淀厚度(mm) 摩 擦 桩 符合设计要求及施工规范 支 承 桩 5 钢筋骨架标高(mm) ±50(十一)桩头处理及检测待桩基混凝土的强度达到设计强度时,处理桩头混凝土至设计标高,对每根桩都进行小应变检测或超声波检测。(十二)钻孔灌注桩施工的注意事项1、钻孔前熟悉图纸,弄清地质情况,根据地质情况确定钻孔的方案方法,对于地质结构为砂层的地层,施工时一定要调整泥浆比重,尽量保证在左右,以使泥浆护壁可以起到保护孔壁的作用。2、钻孔前检查确认孔位地下是否有管线,光缆或其他物体。3、桩轴线的控制:钻机就位施钻时,将钻机底盘调成水平状态,开第一钻时,小心使锥尖对准设计中心,盖上封口板,卡上推钳,试转数圈,用全站仪监控钻杆垂直度,满足要求后,正式开钻,钻进过程中,随时有全站仪监控,保证倾斜度<1/100。4、碰到岩层无法钻进时,需要更换为回旋钻机或冲孔钻机进行施工。在开孔前就配备回旋钻机或冲孔钻机以备急用,以缩短钻孔的停放时间,避免坍孔或缩孔情况发生。5、旋挖钻机在钻进过程中,需要加长钻杆或依据地层更换钻头,在此间歇时间内,需要特别注意孔内情况,以防孔内坍孔。6、在钻孔时,钻机必须配置两套钻头以备更换,在钻进至粉砂层或砂层时,需要特别注意泥浆比重、孔内外水头差等,确保钻进安全、有效的进行。7、在桩基施工时,第一根桩基和第二根计划开钻的桩基要错开,需要跳开相邻桩位的桩基,待对角方向的桩基完毕后才开始施工相邻位置的桩基。8、在终孔和清孔后,应对成孔的孔位、孔深、孔形、孔径、垂直度、泥浆比重、孔底沉淀厚度等进行检验,要求满足设计规定。9、在桩基灌注过程中,必须配备一台砂石泵,如由于灌注过程中发生堵管、气阻或导管提离混凝土面,立即用砂石泵抽出已灌注混凝土,重新清孔后再进行灌注。10、对混凝土的强度、级配、坍落度及混凝土的流动性进行检查。混凝土拌合物应有良好的和易性,在运输和灌注过程中应无显著离析、泌水现象,混凝土保证有足够的初凝时间。灌注时应保持足够的流动性,其坍落度宜为180~200mm。混凝土拌和物中宜掺用外加剂、粉煤灰等材料;首批混凝土拌和物下落后,混凝土应连续灌注。11、必须对每根桩做好相应的施工记录,并按规定留取混凝土试验件,做出试压结果。将上述资料整理好,提交有关部门检查、验收。12、在所有的钻孔灌注桩完成以后,必须对施工场地进行清理,所有的钻渣和泥浆必须清理干净。(十三)钻孔及水下混凝土灌注过程中异常事故及处理办法1、坍孔原因分析:①护筒埋置过浅,周围封填不密漏水;②操作不当,如提升钻头或掏渣筒倾倒,或放钢筋骨架时碰撞孔壁;泥浆稠度小,起不到护壁作用;③泥浆水位高度不够,对孔壁压力小;向孔内加水时流速过大,直接冲刷孔壁;④在松软砂层中钻进,进尺太快。预防及处理措施:坍孔部位不深时,可改用深埋护筒,将护筒周围回填土,夯实,重新钻孔;轻度坍孔,可加大泥浆相对密度和提高水位;严重坍孔,用粘土泥膏投入,待孔壁稳定后采用低速钻进;汛期水位变化过大时,应采取升高护筒,增加水头或用虹吸管等措施保证水头相对稳定;提升钻头,下放钢筋管架应保持垂直,尽量不要碰撞孔壁;在松软砂层钻进时,应控制进尺速度,并用较好泥浆护壁。2、钻孔偏斜原因分析:①桩架不稳、钻杆导架不垂直,钻机磨耗,部件松动;②土层软硬不匀,致使钻头受力不均;③钻孔中遇有较大孤石、探头石;④扩孔较大处,钻头摆动偏向一方;⑤钻杆弯曲,接头不正。预防及处理措施:检查、纠正桩架,使之垂直安置稳固,并对导架进行水平与垂直校正和对钻孔设备加以检修;偏斜过大时,填入土石(砂或砾石)重新钻进,控制钻速;如有探头石,宜用用冲孔机低速将石打碎,倾斜基岩时,可用混凝土填平,待其凝固后再钻。3、卡钻原因分析:①孔内出现梅花孔、探头石、缩孔等未及时处理;②钻头被坍孔落下的石块或误落入孔内的大工具卡住;③入孔较深的钢护筒倾斜或下端被钻头撞击严重变形。预防及处理措施:对于向下能活动的上卡,可用上下提升法,即上、下提动钻头,并配以将钻杆左右拔移、旋转;卡钻后不宜强提,只宜轻提,经提不动时,可用小冲击钻锥冲或用冲、吸的方法将钻锥周围的钻渣松动后再提出;施工中注意保持护筒垂直,防止倾斜;钻头尺寸应统一,下钻应控制钻进速度,不要过快。4、扩孔及缩孔原因分析:①扩孔是因孔壁坍塌或钻机摆过大所致;②缩孔原因是钻锥磨损过甚,焊补不及时或因地层中有软塑土,遇水膨胀后使孔径缩小。预防及处理措施:注意采取防止坍孔和防止钻锥摆过大的措施;注意及时焊补钻锥,并在软塑地层采用失水率小的优质泥浆护壁;已发生缩孔时,宜在该处用钻锥上下反复扫孔以扩大孔径。5、沉碴厚度超标原因分析:清孔泥浆含砂率大、胶体率太小、比重过大。预防及处理措施:控制清孔后泥浆比重小于,保证泥浆的粘度、含沙量、胶体率等满足规范要求,并进行二次清孔,直到满足设计要求。6、水下混凝土灌注时导管进水原因分析:首批混凝土储量不足,或导管底口距孔底间距过大,混凝土下落后不能埋住导管底口以致泥水从底口进入。预防及处理措施:将导管和钢筋笼提出,将散落在孔底的混凝土拌合物用空气吸泥机或抓斗清除,重新灌注。7、导管卡管原因分析:①初灌时隔水栓卡管,或由于混凝土本身的原因如坍落度过小、流动性差、粗骨料过大、拌合物不均匀产生离析、导管接缝处漏水、大雨中运混凝土未加遮盖使混凝土中的水泥浆被冲走,粗骨料集中造成堵塞;②机械发生故障和其他原因使混凝土在导管内停留时间过长,或灌注时间持续过长,最初灌注的混凝土已经初凝,增大了管内混凝土的下落阻力,混凝土堵在管内。预防及处理措施:准备备用机械、掺入缓凝剂,做好配合比,改善混凝土的性能。拔管、吸渣重灌。8、钢筋笼上浮原因分析:导管埋深控制不好。固定钢筋笼的撑杆刚度不够。预防及处理措施:控制导管底口的位置及埋深,在混凝土接近钢筋笼底口时,加大导管埋深,并减缓灌注过程;加强撑杆,增加钢管支撑。
A foundation has the extensively applied realm, is key figures building, large bridge, deep wharf of water and sea the petroleum terrace main foundation form that etc. recent years, a engineering quantity problem influence building structure of the case of the normal usage and safety is a lot construction of the stake have the concealment of the height and the construction quantity of the stakes contain a lot of indeterminations factor, seeing from the angle of a quantity of examination, the method and meanses of the improvement examination, the credibility that the exaltation examination work quantity and examinations assess the result, have the important meaning towards the quantity and safeties that insure an engineering of , is also a research heat of realm to order it a. The low contingency reflect a function with main method is to examine a body structure integrity, if a body blemish position judgment, construction the stake grows to check to settle sex to estimate the etc. with the concrete strength grade, making use of to measure glint a curve signal rows to break a body quantity accurately, expeling the engineering to suffer from, carrying on the evaluation to the quantity of the stake of . This text to the Kelvin not the glint a new method of low contingency of the flexible material a body of line complete sex examination carried on the research. Build up the new model of the Kelvin non- line flexible material an a of the problem motion;Give square distance of the control dynamics of the body, make use of a 维 not the line flexibility originally 构 the relation deduce a stalk toward dint and stalks toward emergency relation, putting forward a not the line flexibility undulates new calculate way of problem;Adopt the FORTRAN language establishment procedure, the number imitates a speed( or move, acceleration) to respond to a form of the timing curve;Exist an establishment of of problem to rise various form database to the integrity finally, is hereafter used for a complete sex examination service. And low contingency glint a method;A body integrity examines 2 phrases
低应变反射波法Low Strain Reflection Wave Method桩身完整性检测Inspection of pile integrity桩基础|pile foundation高层建筑 High-rise buildings(分类词汇:环境资源相关 )大型桥梁super-large bridges 深水码头Deep Water Wharf海上石油平台Offshore oil platform建筑结构building structure施工construction非线性弹性材料nonlinear elastic materials桩基工程质量问题这篇虽然是科技论文,但是我觉得他翻译成“pile foundation quality question”很不妥当,我将他修改成problems of pile foundation quality,,从汉语语法之角度考虑,这里的问题两个字是多余的,去掉更好,你自己看看吧!不确定性因素Incertitude Factors基桩Foundation Pile隐蔽性(Impercephbility)axial strain轴向应变研究热点research hotspot(也有用point的)桩身缺陷位置 positions of pile defects定性估计 qualitative estimation混凝土强度等级concrete strength gradethe signal of reflected_wave curve反射波曲线信号工程隐患Project Concealed Harzard一维波动模型one-way fluctuant model控制体(control volume),本构关系 constitutive relationFORTRAN语言编制程序program written in FORTRAN language响应时程曲线波形时程曲线response time history curvePile foundation is widely used as the main basic structure of high-rise buildings,super-large bridges,deep water wharf and Offshore oil platform. During recent years,there are many bases of pile foundation quality affecting the normal working and safety of the building structures. Pile construction has high impercephbility and whose quality presents many incertitude factors,from an angel of qualitative inspection of the foundation piles, it has important significance for ensuring the quality and safety of foundation pile projects to modify the inspection methods and improving the inspection quality and the reliability of inspection & assessment results,it is also one of the research hotspots in foundation pile field. The main functions of low strain reflection wave method is to inspect the pile integrity, such as the judgment of pile defects positions, the checkout of pile lengths, and the qualitative estimation of the concrete strength grade,the judgment of the pile quality using the signal of reflected_wave curve accurately, the elimination of the project concealed harzard,and the estimation of foundation pile quality. This paper studied on the low strain reflection wave method for measuring of pile integrity made of Kelvin nonlinear elastic materials, set up a new one-way fluctuant model to treat the problems of piles made of Kelvin nonlinear elastic materials, gave out a dynamics equation of control volume,and induced the relation between pile axial forces and axial strain using the constitutive relation of one-way nonlinear elastic materials, put forward a new calculation method for the fluctuation of one-way nonlinear elastic materials, simulated the pile-top speed response time history curve (or displacement, acceleration) numerically using program written in FORTRAN language, finally the author set up a curve database of the foundation piles existing integrity problem for the integrity inspection of foundation piles in the future.
水下灌注桩施工工程中的若干问题(清孔、泥浆护壁、防止钢筋笼上浮、坍孔、断桩)的研究我来帮你吧Q我
桩基础在施工常见问题及处理方法论文
摘 要:正如我们所知道的, 桩基础是地基处理常用的方法之一,其中钻孔灌注桩就是桩基础施工的常用的施工方法,本文以此种方法来分析桩基础在施工过程中常见的问题及提出相应的解决对策。
关键词:桩基础;钻孔灌注桩;质量问题;处理措施
钻孔灌注桩基础是一种可以适应多种地质条件的基础地基建设的形式,在各领域的工程建设中都得到了广泛的应用。所以我们应给予其施工过程高度的重视,掌握施工过程中易出现的问题,并能予以高效率的解决。
1.桩基础施工过程中常见质量问题
桩基础施工过程中常常遇到的问题即是钻孔问题、混凝土灌注施工问题,下面本人将对这两方面进行一系列的分析。
钻孔施工问题
在钻孔施工的过程中,孔口的坍陷将会使钻孔质量无法得到保证,这是因为孔口的坍陷会导致护筒底部的土质变得松散、背后回填土不够结实,有时还会使护筒周围土质受雨水长时间浸泡等因素造成护筒失稳或脱落,这种问题会使护筒移位;有时因为钻机操作人员实施的操作不规范、穿过岩层时发生突变、钻机突然发生、机械故障等原因均有可能导致钻机发生卡钻问题;在钻孔施工时,如果塑性土发生膨胀,将会使成孔后的孔径产生弯曲、孔径局部变小,这将引起钻孔施工不能正常进行;在新疆这类松软土层中,如果进尺的速度较快、吊装钢筋笼碰撞孔壁或是未按照施工工艺的要求制备符合标准的泥浆等因素均会造成坍孔问题的发生,从而引起钻孔施工问题;在钻孔是,如果钻机的钢丝绳发生断裂、钻机出现机械故障或者钻孔发生坍塌,会使钻头掉落到孔底而无法进行正常的作业。
水下混凝土灌问题
这类施工问题主要是由封底失败、卡管、钢筋笼上浮等原因造成的。产生封底失败的主要原因是孔底沉渣厚度超过所规定的标准范围,从而引起了混凝土在灌注后没有实现水下混凝土封底,从而引起施工问题;因为混凝土具有和易性差、灌注混凝土时冲击力不足的特点,此外混凝土中还含有很多大块骨料或受潮凝固的水泥块,这就引发了卡管问题,无法正常的进行浇筑混凝土的操作;由于钢筋笼制作、堆放、吊装、运输等过程不符合施工的规范要求,钢筋骨架内径与导管外壁间距没有符合规定的尺码,导管在提升过程中挂带了钢筋笼,或是由于混凝土浇筑速度过快,混凝土面升至钢筋笼底部产生向上“浮力”导致钢筋笼上浮;由于混凝土的配合比不当、原材料也未能符合规定或灌注混凝土过程中局部坍塌的杂物土质等侵入混凝土及混凝土和易性差等因素,都会直接或间接的发生断桩的施工问题。
2.针对于施工过程中常见的问题的处理措施
钻孔施工所发生的问题的应对处理措施
首先,护筒埋入在土层中的深度一定要大于水头高度,而且必须穿过松散土层、淤泥层,此外,护筒四周的回填土必须夯填密实;再者,假如发生卡钻的施工问题是,我们不要直接强行拔出,应该晃动大绳以便钻头松动后提起或者插入高压水管置换泥浆,也就是先下放钻头而后迅速上提使岩层突变物受强力冲击而破碎或回缩,从而提起钻头,切忌不能蛮拉;在施工时,应用的是加大泥浆密度、加高水头、埋深护筒等方法进行操作,在坍孔问题严重时,我们必须回填重新钻孔,以免加大了施工问题;如果采用冲击法进行钻孔,可利用投黏土块夹小片石,用低锤冲击将其挤入孔壁来制止坍孔,而当钢筋笼吊装造成坍孔时立即将钢筋笼吊出,添加泥浆护壁将坍陷物清理干净,确认不再坍塌后重新安装钢筋笼。
水下混凝土灌所发生问题的应对处理措施
首先,我们要利用导管内安装高压风管的方法重新清孔,将已灌注混凝土彻底的清理干净,然后再重新开始水下混凝土浇筑,也可以先拆除导管,拔出钢筋笼,将未灌注混凝土部分回填,稍后用钻机钻头清除已灌注混凝土,然后再重新开始浇筑水下混凝土;在施工时,先慢慢的提升导管,而后快速下落导管,这样可加大混凝土灌注量而后快速提升再快速下落以冲击导管,便于导管的疏通,还可以适当的加长上部导管的长度,然后以一次性较大量混凝土来冲击混凝土达到疏通的目的;最后,我们应该关注混凝土浇注过快引起的钢筋笼上浮问题,面对这类施工问题,我们应立即控制混凝土的浇筑量和浇灌速度,并且反复上下摇动导管,采用这种方法,钢筋笼上浮现象还是得不到根治,就必须立即中止浇灌混凝土,拔出导管侯向孔内回填黏土,该桩作废处理,并及时与监理人员、设计人员联系重新补桩。
3.桩基础施工过程中的注意事项
钻孔过程中的注意事项
在钻孔前,应先对桩位反复进行测量,测量的同时要在护筒上用交叉十字线的'方法涂抹红漆,这样将方便于钻孔过程及成孔后桩位的技术施工核实。在钻孔过程中,我们必须详细准确地记录地层地质的变化情况。要做到详细、准确、认真地记录钻孔记录,技术人员积极了解地质变化情况并及时向上级反映相关情况起着相当关键的作用,尤其是能够为工程变更提供合理的依据和真实数据。为了准确地了解和掌握地质变化情况,最好的办法是对钻渣及时进行取样并留取渣样。
加强成孔检测
首先,施工人员应仔细查看详细真实的钻孔记录,切实准确得掌握不稳定的地层,依照不同的地形制定切实合理的灌注方案。第二,要详细记录各项检测数据,尤其是孔深的记录,这样做的主要目的在于计算泥浆沉淀速度和深度,便于做出合理的判断和采取合理的灌注办法。最后,我们应该认真做好灌前准备工作,根据土层的不同质地,应做好导管的打压试验,以确保导管的密水性符合要求。
4.结语
众所周知,钻孔桩基础是地基处理的主要方式之一,那么它施工的好坏将决定工程施工的好坏,所以我们应予以高度的重视,了解在施工的环节中可能出现哪些问题,提前做好准备,以预防为主,规范施工工序流程,做好质量控制,对可能出现的质量问题制定切实有效的防范措施,减少质量问题,杜绝质量事故的发生。
参考文献:
[1] 中国建筑科学研究院. JGJ94—2008 建筑桩基技术规范[S]. 北京:中国建筑工业出版社,2008.
355 浏览 5 回答
310 浏览 6 回答
143 浏览 5 回答
326 浏览 4 回答
117 浏览 3 回答
131 浏览 5 回答
284 浏览 4 回答
164 浏览 4 回答
341 浏览 5 回答
110 浏览 4 回答
231 浏览 5 回答
152 浏览 4 回答
139 浏览 5 回答
314 浏览 2 回答
105 浏览 3 回答