【abstract】 gz an overview of the river in xinjiang can be hidden resources and develop the different sections of the cascade development programs, from the steps of engineering geological conditions, water indicators, hydraulic layout, construction conditions, flooding and engineering operation management options recommended by the development program, in recommending the adoption of programs based on the analysis argues that the choice of the recent development of the project.
【key words】water conservancy and hydropower project; hydropower planning; development programs; recommended recent works; xinjiang river gz
1. gz河河段概况
新疆gz河地处新疆的西南部,塔里木盆地西部边缘,地处克州和喀什两地州,北与克孜河相邻,南与库山河相依,东与叶尔羌河相望。Www.133229.cOmgz河上游由西北源的木吉河和南源的康西瓦河汇流而成,流经克州的阿克陶县及喀什地区的疏附、疏勒、岳普湖等县境内,最后消失在岳普湖县境内以东。gz河全长260km,总落差5889.8m,水能资源理论蕴藏量600.1mw,gz河地势自西南向东北倾斜,右岸高而左岸稍低。
2. gz河河段水能资源
gz河水能蕴藏量为600.1mw,主要集中在中游河段。gz河水能资源具有以下特点:布仑口断面占出山口断面径流量的45.73%;河段落差2245m,河段长157km,河段平均坡降14.30‰,河段径流分散,河段平均纵坡较大,河段出力194.5mw,单位河段水流出力为1.24mw/km,水能理论蕴藏量仅占全河的32.5%。
3. gz河梯级开发方案拟定
gz河流域拟定的梯级布置方案应以满足流域水资源配置方案为前提,控制性工程布局应能够有效控制流域的水资源,并和水资源的开发利用紧密结合起来,同时满足规划确定的流域治理开发目标。因此,梯级开发方案必须服从流域水资源配置方案的需要。根据这一基本原则拟定梯级开发方案进行比较,根据开发的可行性、 经济 性,确定合理的梯级开发方案。依据梯级布置原则,本次中游河段水电规划梯级开发共拟定了三种方案,三组梯级开发方案为:
方案一(1库7级方案),即:布仑口+盖孜+克勒麦拉克+托尕依+博孜尤勒滚+亚勒马+吐木休克。
方案二(1库5级方案),即:布仑口+盖孜+托尕依+乌依塔克+吐木休克。在方案一的基础上,合并部分梯级电站,并在支流玛尔坎苏河上布置乌依塔克水库。
方案三(1库4级方案),即:布仑口+盖孜+托尕依+吐木休克。在方案二的基础上,合并部分梯级电站。
4. gz河梯级开发方案拟定
通过对各梯级开发方案的工程地质、动能指标、水工布置、施工条件、运行管理、环境影响、水库淹没、工程投资及经济指标的综合比较,方案二地质条件较优,动能指标较好,水工布置较为简单,施工条件良好,运行管理简单方便,环境影响较小,工程投资省,经济效益最优,所以各方面均优于其它方案。因此,本次规划确定方案二(1库5级开发方案)为推荐方案。